Chittenden Locks Upcoming 2020 Operational Schedule
The Hiram M. Chittenden locks large chamber resumed full operations 4:30pm December 23.
The maintenance crew resolved a limit switch that affected all the miter gates and cleared debris from under a miter gate.
The small chamber is scheduled to close January 6-24 for annual maintenance. The large chamber is scheduled to be closed February 12-April 5 for the second extended closure for the Stoney Gate Valve Project.
For more information about scheduled and projected Chittenden Locks closures, visit https://go.usa.gov/xVtpE. For closures and other activities visit the Locks' Web site at http://bit.ly/BallardLocks.