Dock 2 Roofs - July and August 2008
#1
July 2, 2008 - 10:14am
Dock 2 Roofs - July and August 2008
Dock #2 re-roofing project to commence about July 10, 2008.
Moorage under roof units #1, 2, 3, & 4 as numbered from shore outward are affected. The slips are numbered from 209 through 257.
The latest start date for teardown of roof number 24, is Monday, July 14 with scaffold staging, probably to be installed late in the week of July 7.
I leave this topic for comments or questions from any of you.
Arthur... thanks very much for your patience and cooperation.