QCYC Boat pump-out

3 posts / 0 new
Last post
#1 October 7, 2012 - 1:31pm
DickGeving

QCYC Boat pump-out

Well folks it's almost done. The new sewage pump out, located next to the dinghy crane, is about 90% completed.  The trench took 17 members three days to dig, add the double pipe, cover, and cement in.  What a great job they did!.  Jerry had a stand made and he mounted the pump on Wednesday and Thursday.  Friday we did a test and found we can pump 20 gallons a minute.  A box is being constructed over both the crane and pumpout so they are pleasing to look at and give protection to our valuable equipment. The controls will be via card access.  We anticipate a wave of your card will give you fifteen minutes plus or minus use.  If you need more wave your card again. The time is limited as we have found some members forget to turn off the crane in the past and it's not good for the hydraulics.

A huge THANK YOU to Captain Zuvich for his design, support, and very hard work.